11. A certain industrial loom weaves 0.128 meters of cloth every second. Approximately how many seconds will it take for the loom to weave 25 meters of cloth? | |
A. 205 | B. 200 |
C. 180 | D. 195 |
answer with explanation
Answer: Option D
Explanation:
Let the required number of seconds be
More cloth, More time, (direct proportion)
Hence we can write as
(cloth) 0.128 : 25 :: 1 :
Explanation:
Let the required number of seconds be
More cloth, More time, (direct proportion)
Hence we can write as
(cloth) 0.128 : 25 :: 1 :
12. A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time,each persons now working 9 hours a day. | |
A. 160 | B. 150 |
C. 24 | D. 56 |
answer with explanation
Answer: Option D
Explanation:
Solution 1 (Chain Rule)
Persons worked = 104
Number of hours each person worked per day = 8
Number of days they worked = 30
Work completed
Remaining days = 56 - 30 = 26
Remaining Work to be completed
Let the total number of persons who do the remaining work
Number of hours each person needs to be work per day = 9
More days, less persons (indirect proportion)
More hours, less persons (indirect proportion)
More work, more persons (direct proportion)
Hence we can write as
Number of additional persons required = 160 - 104 = 56
Solution 2 (Using Time and Work)
Persons worked = 104
Number of hours each person worked per day = 8
Number of days they worked = 30
Work completed
Remaining days = 56 - 30 = 26
Remaining Work to be completed
Let the total number of persons who do the remaining work
Number of hours each person needs to be work per day = 9
Amount of work 1 person did in 1 day, working 1 hours a day
Now, the amount of work person should do in 1 day, working 1 hours a day
Number of additional persons required = 160 - 104 = 56
Solution 3 (Using Time and Work)
Persons worked (M1) = 104
Number of hours each person worked per day (H1) = 8
Number of days they worked (D1) = 30
Work completed (W1)
Remaining days (D2)= 56 - 30 = 26
Remaining Work to be completed (W2)
Let the total number of persons who do the remaining work (M2)
Number of hours each person needs to be work per day (H2) = 9
Number of additional persons required = 160 - 104 = 56
Explanation:
Solution 1 (Chain Rule)
Persons worked = 104
Number of hours each person worked per day = 8
Number of days they worked = 30
Work completed
Remaining days = 56 - 30 = 26
Remaining Work to be completed
Let the total number of persons who do the remaining work
Number of hours each person needs to be work per day = 9
More days, less persons (indirect proportion)
More hours, less persons (indirect proportion)
More work, more persons (direct proportion)
Hence we can write as
Number of additional persons required = 160 - 104 = 56
Solution 2 (Using Time and Work)
Persons worked = 104
Number of hours each person worked per day = 8
Number of days they worked = 30
Work completed
Remaining days = 56 - 30 = 26
Remaining Work to be completed
Let the total number of persons who do the remaining work
Number of hours each person needs to be work per day = 9
Amount of work 1 person did in 1 day, working 1 hours a day
Now, the amount of work person should do in 1 day, working 1 hours a day
Number of additional persons required = 160 - 104 = 56
Solution 3 (Using Time and Work)
If men can do work in days working hours per day and men can do work in days working hours per day where all men work at the same rate, then
Persons worked (M1) = 104
Number of hours each person worked per day (H1) = 8
Number of days they worked (D1) = 30
Work completed (W1)
Remaining days (D2)= 56 - 30 = 26
Remaining Work to be completed (W2)
Let the total number of persons who do the remaining work (M2)
Number of hours each person needs to be work per day (H2) = 9
Number of additional persons required = 160 - 104 = 56
13. men working hours per day can do units of a work in days. How much work can be completed by men working hours per day in days? | |
A. units | B. units |
C. units | D. units |
answer with explanation
Answer: Option B
Explanation:
Solution 1 (Chain Rule)
Let amount of work completed by men working hours per in days = units
More men, more work(direct proportion)
More hours, more work(direct proportion)
More days, more work(direct proportion)
Hence we can write as
Solution 2 (Using Time and Work)
Amount of work completed by 1 man in 1 day, working 1 hours a day
Amount of work completed by men in days, working hours a day
Solution 3 (Using Time and Work)
M1
H1
D1
W1
M2
D2
H2
Let W2= w
Explanation:
Solution 1 (Chain Rule)
Let amount of work completed by men working hours per in days = units
More men, more work(direct proportion)
More hours, more work(direct proportion)
More days, more work(direct proportion)
Hence we can write as
Solution 2 (Using Time and Work)
Amount of work completed by 1 man in 1 day, working 1 hours a day
Amount of work completed by men in days, working hours a day
Solution 3 (Using Time and Work)
If men can do work in days working hours per day and men can do work in days working hours per day where all men work at the same rate, then
M1
H1
D1
W1
M2
D2
H2
Let W2= w
14. 21 goats eat as much as 15 cows. How many goats eat as much as 35 cows? | |
A. 49 | B. 32 |
C. 36 | D. 41 |
answer with explanation
Answer: Option A
Explanation:
15 cows ≡ 21 goats
1 cow ≡ goats
35 cows ≡ goats
≡ goats ≡ 7 × 7 goats ≡ 49 goats
Explanation:
15 cows ≡ 21 goats
1 cow ≡ goats
35 cows ≡ goats
≡ goats ≡ 7 × 7 goats ≡ 49 goats
15. A flagstaff 17.5 m high casts a shadow of length 40.25 m. What will be the height of a building, which casts a shadow of length 28.75 m under similar conditions? | |
A. 12.5 m | B. 10.5 m |
C. 14 | D. 12 |
answer with explanation
Answer: Option A
Explanation:
Solution 1 (Chain Rule)
Let the required height of the building be meter
More shadow length, More height(direct proportion)
Hence we can write as
(shadow length) 40.25 : 28.75 :: 17.5 :
Solution 2
shadow of length 40.25 m ≡ 17.5 m high
shadow of length 1 m ≡ m high
shadow of length 28.75 m ≡ m high = 12.5 m high
Explanation:
Solution 1 (Chain Rule)
Let the required height of the building be meter
More shadow length, More height(direct proportion)
Hence we can write as
(shadow length) 40.25 : 28.75 :: 17.5 :
Solution 2
shadow of length 40.25 m ≡ 17.5 m high
shadow of length 1 m ≡ m high
shadow of length 28.75 m ≡ m high = 12.5 m high
16. Running at the same constant rate, 6 identical machines can produce a total of 270 bottles per minute. At this rate, how many bottles could 10 such machines produce in 4 minutes? | |
A. 1800 | B. 900 |
C. 2500 | D. 2700 |
answer with explanation
Answer: Option A
Explanation:
Let required number of bottles be
More machines, more bottles(direct proportion)
More minutes, more bottles(direct proportion)
Hence we can write as
Explanation:
Let required number of bottles be
More machines, more bottles(direct proportion)
More minutes, more bottles(direct proportion)
Hence we can write as
17. A person works on a project and completes of the job in 10 days. At this rate, how many more days will he it take to finish the job? | |
A. 7 | B. 6 |
C. 5 | D. 4 |
answer with explanation
Answer: Option B
Explanation:
Solution 1 (Chain Rule)
Number of days he worked = 10
Work completed
Let the required number of days
Remaining Work to be completed
More work, more days(direct proportion)
Hence we can write as
(Work) : :: 10 :
Solution 2 (Using Time and Work)
Number of days he worked = 10
Work completed
Let the required number of days
Remaining Work to be completed
Amount of work 1 person did in 1 day
Now, the amount of work 1 person should do in days
Solution 3 (Using Time and Work)
Here,
M1 = M2
H1 = H2
D1 = 10
W1
Let D2
W2
Hence, the equation can be written as
Explanation:
Solution 1 (Chain Rule)
Number of days he worked = 10
Work completed
Let the required number of days
Remaining Work to be completed
More work, more days(direct proportion)
Hence we can write as
(Work) : :: 10 :
Solution 2 (Using Time and Work)
Number of days he worked = 10
Work completed
Let the required number of days
Remaining Work to be completed
Amount of work 1 person did in 1 day
Now, the amount of work 1 person should do in days
Solution 3 (Using Time and Work)
If men can do work in days working hours per day and men can do work in days working hours per day where all men work at the same rate, then
Here,
M1 = M2
H1 = H2
D1 = 10
W1
Let D2
W2
Hence, the equation can be written as
18. A fort had provision of food for 150 men for 45 days. After 10 days, 25 men left the fort. Find out the number of days for which the remaining food will last. | |
A. 44 | B. 42 |
C. 40 | D. 38 |
answer with explanation
Answer: Option B
Explanation:
Given that fort had provision of food for 150 men for 45 days
Hence, after 10 days, the remaining food is sufficient for 150 men for 35 days
Remaining men after 10 days = 150 - 25 = 125
Assume that after 10 days,the remaining food is sufficient for 125 men for days
More men, Less days (Indirect Proportion)
(men) 150 : 125 :: : 35
i.e., the remaining food is sufficient for 125 men for 42 days
Explanation:
Given that fort had provision of food for 150 men for 45 days
Hence, after 10 days, the remaining food is sufficient for 150 men for 35 days
Remaining men after 10 days = 150 - 25 = 125
Assume that after 10 days,the remaining food is sufficient for 125 men for days
More men, Less days (Indirect Proportion)
(men) 150 : 125 :: : 35
i.e., the remaining food is sufficient for 125 men for 42 days
19. If the price of 357 apples is Rs.1517.25, what will be the approximate price of 49 dozens of such apples? | |
A. Rs. 2500 | B. Rs. 2300 |
C. Rs. 2200 | D. Rs. 1400 |
answer with explanation
Answer: Option A
Explanation:
Solution 1 (Chain Rule)
Let the required price be
More apples, More price(direct proportion)
Hence we can write as
(apples) 357 : (49 × 12) :: 1517.25 :
Solution 2
price of 357 apples = Rs.1517.25
price of 1 apple = Rs.
price of 49 dozens apples = Rs.
Explanation:
Solution 1 (Chain Rule)
Let the required price be
More apples, More price(direct proportion)
Hence we can write as
(apples) 357 : (49 × 12) :: 1517.25 :
Solution 2
price of 357 apples = Rs.1517.25
price of 1 apple = Rs.
price of 49 dozens apples = Rs.
20. On a scale of a map 0.6 cm represents 6.6km. If the distance between two points on the map is 80.5 cm , what is the the actual distance between these points? | |
A. 885.5 km | B. 860 km |
C. 892.5 km | D. 825 km |
answer with explanation
Answer: Option A
Explanation:
Solution 1 (Chain Rule)
Let the required actual distance be km
More scale distance, More actual distance(direct proportion)
Hence we can write as
(scale distance) 0.6 : 80.5 :: 6.6 :
Solution 2
0.6 cm in map ≡ actual distance of 6.6 km
1 cm in map ≡ km
80.5 cm in map ≡ km = 885.5 k
m
Explanation:
Solution 1 (Chain Rule)
Let the required actual distance be km
More scale distance, More actual distance(direct proportion)
Hence we can write as
(scale distance) 0.6 : 80.5 :: 6.6 :
Solution 2
0.6 cm in map ≡ actual distance of 6.6 km
1 cm in map ≡ km
80.5 cm in map ≡ km = 885.5 k
m
No comments:
Post a Comment