Problems on Chain Rule - Solved Examples
1. If the cost of metres of wire is rupees, then what is the cost of metres of wire at the same rate? | |
A. | B. |
C. | D. |
answer with explanation
Answer: Option C
Explanation:
cost of metres of wire = Rs.
cost of 1 metre of wire = Rs.
cost of metre of wire = Rs.
Explanation:
cost of metres of wire = Rs.
cost of 1 metre of wire = Rs.
cost of metre of wire = Rs.
2. In a dairy farm, 40 cows eat 40 bags of husk in 40 days. In how many days one cow will eat one bag of husk? | |
A. 1 | B. 40 |
C. 20 | D. 26 |
answer with explanation
Answer: Option B
Explanation:
Assume that in days, one cow will eat one bag of husk.
More cows, less days (Indirect proportion)
More bags, more days (direct proportion)
Hence we can write as
Explanation:
Assume that in days, one cow will eat one bag of husk.
More cows, less days (Indirect proportion)
More bags, more days (direct proportion)
Hence we can write as
3. If 7 spiders make 7 webs in 7 days, then how many days are needed for 1 spider to make 1 web? | |
A. 1 | B. 7 |
C. 3 | D. 14 |
answer with explanation
Answer: Option B
Explanation:
Let, 1 spider make 1 web in days.
More spiders, Less days (Indirect proportion)
More webs, more days (Direct proportion)
Hence we can write as
Explanation:
Let, 1 spider make 1 web in days.
More spiders, Less days (Indirect proportion)
More webs, more days (Direct proportion)
Hence we can write as
4. 4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days? | |
A. 4 | B. 16 |
C. 8 | D. 1 |
answer with explanation
Answer: Option B
Explanation:
Let the required number of mats be
More mat-weavers, more mats (direct proportion)
More days, more mats (direct proportion)
Hence we can write as
Explanation:
Let the required number of mats be
More mat-weavers, more mats (direct proportion)
More days, more mats (direct proportion)
Hence we can write as
5. If a quarter kg of potato costs 60 paise, how many paise does 200 gm cost? | |
A. 65 paise | B. 70 paise |
C. 52 paise | D. 48 paise |
answer with explanation
Answer: Option D
Explanation:
Solution 1 (Chain Rule)
Let 200 gm potato costs paise
Cost of Kg potato = 60 Paise
=> Cost of 250 gm potato = 60 Paise
More quantity, More Paise (direct proportion)
Hence we can write as
(quantity) 200 : 250 :: : 60
Solution 2
Cost of kg potato = 60 Paise
=> Cost of 250 gm potato = 60 Paise
=> Cost of 200 gm potato
Explanation:
Solution 1 (Chain Rule)
Let 200 gm potato costs paise
Cost of Kg potato = 60 Paise
=> Cost of 250 gm potato = 60 Paise
More quantity, More Paise (direct proportion)
Hence we can write as
(quantity) 200 : 250 :: : 60
Solution 2
Cost of kg potato = 60 Paise
=> Cost of 250 gm potato = 60 Paise
=> Cost of 200 gm potato
6. In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered to with remaining meal? | |
A. 50 | B. 30 |
C. 40 | D. 10 |
answer with explanation
Answer: Option B
Explanation:
Meal for 200 children = Meal for 120 men
=> Meal for 1 child = Meal for men
=> Meal for 150 children
= Meal for = Meal for 90 men
Total meal available = Meal for 120 men
Remaining meal
= Meal for 120 men - Meal for 90 men
= Meal for 30 men
Explanation:
Meal for 200 children = Meal for 120 men
=> Meal for 1 child = Meal for men
=> Meal for 150 children
= Meal for = Meal for 90 men
Total meal available = Meal for 120 men
Remaining meal
= Meal for 120 men - Meal for 90 men
= Meal for 30 men
7. 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work? | |
A. 26 | B. 22 |
C. 12 | D. 24 |
answer with explanation
Answer: Option D
Explanation:
Solution 1 (Chain Rule)
Let the required number of days be
More men, less days (indirect proportion)
Hence we can write as
(men) 36 : 27 :: : 18
Solution 2 (Using Time and Work)
Amount of work 36 men can do in 1 day
Amount of work 1 man can do in 1 day
Amount of work 27 men can do in 1 day
27 men can complete the work in 24 days
Solution 3 (Using Time and Work)
In this case,
= 36, = 27
= 18,
(∵ We can assume like this as these vales are not explicitly given)
Hence,
Explanation:
Solution 1 (Chain Rule)
Let the required number of days be
More men, less days (indirect proportion)
Hence we can write as
(men) 36 : 27 :: : 18
Solution 2 (Using Time and Work)
Amount of work 36 men can do in 1 day
Amount of work 1 man can do in 1 day
Amount of work 27 men can do in 1 day
27 men can complete the work in 24 days
Solution 3 (Using Time and Work)
If men can do work in days working hours per day and men can do work in days working hours per day where all men work at the same rate, then
In this case,
= 36, = 27
= 18,
(∵ We can assume like this as these vales are not explicitly given)
Hence,
8. A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. If the smaller wheel has made 21 revolutions, what will be the number of revolutions made by the larger wheel? | |
A. 15 | B. 12 |
C. 21 | D. 9 |
answer with explanation
Answer: Option D
Explanation:
Let the number of revolutions made by the larger wheel be
More cogs, less revolutions (Indirect proportion)
Hence we can write as
(cogs) 6 : 14 :: : 21
Explanation:
Let the number of revolutions made by the larger wheel be
More cogs, less revolutions (Indirect proportion)
Hence we can write as
(cogs) 6 : 14 :: : 21
9. 3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day should 4 pumps work in order to empty the tank in 1 day? | |
A. 10 | B. 12 |
C. 8 | D. 15 |
answer with explanation
Answer: Option B
Explanation:
Let the required hours needed be
More pumps, less hours (Indirect proportion)
More Days, less hours (Indirect proportion)
Hence we can write as
Explanation:
Let the required hours needed be
More pumps, less hours (Indirect proportion)
More Days, less hours (Indirect proportion)
Hence we can write as
10. 39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work? | |
A. 9 | B. 12 |
C. 10 | D. 13 |
answer with explanation
Answer: Option D
Explanation:
Solution 1 (Chain Rule)
Let the required number of days be
More persons, less days (indirect proportion)
More hours, less days (indirect proportion)
Hence we can write as
Solution 2 (Using Time and Work)
Amount of work 39 persons can do in 1 day, working 5 hours a day
Amount of work 1 person can do in 1 day, working 5 hours a day
Amount of work 1 person can do in 1 day, working 1 hours a day
Amount of work 30 person can do in 1 day, working 1 hours a day
Amount of work 30 person can do in 1 day, working 6 hours a day
=> 30 persons can complete the work ,working 6 hours a day in 13 days
Solution 3 (Using Time and Work)
In this case,
M1 = 39, M2 = 30
D1 = 12, D2 =
W1 = W2
H1 = 5, H2 = 6
Hence,
Explanation:
Solution 1 (Chain Rule)
Let the required number of days be
More persons, less days (indirect proportion)
More hours, less days (indirect proportion)
Hence we can write as
Solution 2 (Using Time and Work)
Amount of work 39 persons can do in 1 day, working 5 hours a day
Amount of work 1 person can do in 1 day, working 5 hours a day
Amount of work 1 person can do in 1 day, working 1 hours a day
Amount of work 30 person can do in 1 day, working 1 hours a day
Amount of work 30 person can do in 1 day, working 6 hours a day
=> 30 persons can complete the work ,working 6 hours a day in 13 days
Solution 3 (Using Time and Work)
If men can do work in days working hours per day and men can do work in days working hours per day where all men work at the same rate, then
In this case,
M1 = 39, M2 = 30
D1 = 12, D2 =
W1 = W2
H1 = 5, H2 = 6
Hence,
No comments:
Post a Comment