Showing posts with label Time and Work. Show all posts
Showing posts with label Time and Work. Show all posts

Thursday, 17 August 2017

Time and work



Time and work

This chapter is based on the concept of direct and inverse variations. We need to understand relation among time, work done and number of employees working.

Assuming that all employees work with the same efficiency, we can conclude that work done is directly proportional to number of employees working and number of days to complete the work is inversely proportional to number of employees working. 

For example if a person does a work in 10 days then in 1 day he does only one tenth of the work. 

For example it two men can complete a work working alone in 10 and 20 days respectively, then one day’s work of both the men will be 
Thus the total can be completed by both of them in 

Important points: 

 If A can do a piece of work in X days, then A’s one day’s work =1/Xth part of whole work. 
  If A’s one day’s work =1/Xth part of whole work, then A can finish the work in X days. 
➂ If A can do a piece of work in X days and B can do it in Y days then A and B working together will do the same work in
 If A, B and C can do a work in X, Y and Z days respectively then all of them working together can finish work in

Example: If X can do a work in 10 day, Y can do the same work in 20 days, Z can do double of the work in 30 days. If all 3 started working together, find the total time required to complete the work. 
Solution: 
(i) Unitary Method:
(ii) LCM Method:
CONCEPT of MAN DAYS

Assuming that all men work with same efficiency, we can conclude that if the work done is constant then the number of days is inversely proportional to the number of men working. For example, if we say that 20 men can do a work in 30 days, this means that total work is 20x30 man days = 600 man days, which means that the same work can be done by 10 men in 60 days or 60 men can do in 10 days only etc. So for a constant work number 
of man days is constant.
where M is the number of men 
⇒ MD = constant 
Thus we obtain a relationship 

If work is not constant then it is directly proportional to both number of men and number of days 
Where MD is equivalent to number of man days. 

Example: 10 men or 20 women or 30 children, can do a work in 15 days. If 10 men, 12 women and 18 children work on the same work, find the time in which work can be competed. 
Solution: 
We see that 10 men are equivalent to 20 women that is equivalent to 30 children 
Hence 1 man = 2 women = 3 children 
Total work is 10 × 15 = 150 man days 
10 men, 12 women and 18 children are equivalent to 10 + (12/2) + (18/3) = 22 men. 
Hence time taken to complete the work 
= 150/22 = 75/11 = 6 (9/11) days. 

ALTERNATE WORKING
In the following example, we will discuss how to find the total time taken to complete the work, if the two or more workers are not working together but they are working on alternate days. 
Suppose A and B are the two workers working on a project such that A and B can complete a work working alone in 20 and 12 days respectively. Now they are working on alternate day, now to find the total time required to complete the work, there can be two cases: 
(a) Starting with ‘A’
(b) Starting with ‘B’
In these types of questions work done on the first day is not same as the work done on the second day but not work done in first two days is same as the work done in the next two days and that is same as the work done in the next two days and so on.
AB  AB  AB ………
Work done in 2 days 
If we assume 2 days to be one cycle and total work is always considered as 1 unit, then approximate number of cycles required to complete the work =15/2=7 (integral number) 
Total work done after 7 complete cycles
 Hence the remaining work is 1/15 

(1) A started the work: In one day A completes 1/20th of the work, hence 1/15th of the work will be completed in more than one day. A will complete 1/20th part and the remaining work will be done by B. 
Remaining work =

Now B will complete the remaining work in 1/60×12=1/5 days. Total time taken will be: 
(2) B started the work: B will complete the remaining work (1/15 th)of the complete work in 

PIPES AND CISTERNS
This is the topic which gives the relation between the time required to fill or empty the tank with the taps opened or closed. 
Till the time we have only defined the concept of positive work but in the problems related to pipes and cisterns we have to define the concept of negative work also. Concept of negative work is defined as when the work is done against the requirement. 

Example: A tap can fill a tank in 16 minutes and another can empty it in 8 minutes. If the tank is already ½ full and both the taps are opened together, will the tank be filled or emptied? How long will it take before the tank is either filled or emptied completely? 
Solution: 
If both the pumps are opened together, then the tank will be emptied because the working efficiency of pump empting is more than that of the pump filling it. Thus in 1 min net proportion of the volume of tank filled 

(Which means that tank will be emptied 1/6th in one minute.) 
Hence in 8 minutes half of the tank will be emptied. 

Some Important Tricks

 If A and B working together, can finish a piece of work in x days, B and C in y days, C and A in z days, then 
A, B and C working together will complete the job in 



 A alone will complete the job in 



 C alone will complete the job in 

 
If A can complete a work in x days and B is k times efficient than A, then the time taken by both A and B, working together to complete the work is 



If A and B, working together, can complete a work in x days and B is k times efficient than A, 
then the time taken by – 
A working alone to complete the work in 
→ (k + 1) x
B working alone to complete the work is 


 If A working alone takes ‘a’ days more than A and B, and B working alone takes ‘b’ days more than A and B together, then the number of days taken by A and B, working together, to finish a job is given by
  If A can complete a/b part of work in X days, then c/d part of the work will be done in
  If ‘a’ men and ‘b’ women can do a piece of work in ‘n’ 
days, then ‘c’ men and ‘d’ women can do the work in 

Wednesday, 16 August 2017

SSC CGL Tier-II



Dear students,
Now you have checked scores and start preparing for the Tier -II . we are going to provide Quant quizzes specifically for the mains exam . 
Now, we're going to provide Short Tricks with Example Questions, So that you can familiarise yourself with tricky scenarios of Quant. Every day we'll post Some useful Tricks for SSC CGL Tier -II, and it will help you in scoring respected marks.
                                 
                               Percentage wise distribution of Topics For Tier-II                                          


TIME AND WORK


1. If A and B working together, can finish a piece of work in x days, B and C in y days, C and A in z days, then
       (a) A, B and C working together will complete the job in
           = 
 


2. (a) If A can complete a work in x days and B is k times efficient than A, then the time taken by both A and B, working together to complete the work is 




(b) If A and B, working together, can complete a work in x days and B is k times efficient than A, then the time taken by - 


3. If A working alone takes ‘a’ days more and B working alone takes ‘b’ days more than A and B together, then the number of days taken by A and B, working together, to finish a job is given by √ab .


Time and Work


Quick Study Notes and Quiz on Time and Work


TIPS FOR SOLVING QUESTIONS RELATED TO TIME AND WORK:
1. The total work is taken as 1.
2. If A can do a piece of work in 'n' days, ,then A's 1 day's work is equal to = 1/n
3. If A's 1 day's work = 1/n, then A can complete the work in 'n' days.
4. If A is thrice as good a workman as B, then
    Ratio of work done by A and B = 3 : 1.
    Ratio of time taken by A and B to finish the work = 1 : 3.
5.If ‘M1’ persons can do ‘W1’ work in ‘D1’ days and ‘M2’ persons can do W2 work in D2, days then we have a very general formula in the relationship of M1 D1 W2 = M2 D2 W1. The above relationship can be taken as a very basic and all-in-one formula. We also derive 
A) More men less days and conversely more days less men. 
B) More men more work and conversely more work more men. 
C) More days more work and conversely more work more days. 

6.If we include the working hours (say T1 and T2) for the two groups then the relationship is 
M1 D1 T1 W2 = M2 D2 T2 Q1
Again, if the efficiency (Say E1 and E2) of the persons in two groups is different then the relationship is
M1 D1 T1 E1 W2 = M2 D2 T2 E2 W1
Now, we should go ahead starting with simpler to difficult and more difficult questions. 

Questions on Above Formulaes

1.A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
A. Rs. 375
B. Rs. 400
C. Rs. 600
D.Rs. 800

2. Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?
A. 3 pm
B. 2 pm
C. 1:00 pm
D. 11 am

3. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
A. 20 days
B. 22 1/2days
C. 25 days
D. 30 days

4. P is 30% more efficient than Q. P can complete a work in 23 days. If P and Q work together, how much time will it take to complete the same work?
A. 9
B. 11
C. 13
D. 15

5. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
A. 4 days
B. 5 days
C. 6 days
D. 7 days

6.40 men can cut 60 trees in 8 hours. If 8 men leave the job how many trees wiil be cut in 12 hours?
A. 74
B. 82
C. 72
D. 73

7.A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
A. 8 hours
B. 10 hours
C. 12 hours
D. 24 hours

8. P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?
A. 5 days
B. 10 days
C. 14 days
D. 22 days

9. If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.
A. 12
B. 14
C. 16
D. 18

10. Assume that 20 cows and 40 goats can be kept for 10 days for Rs.460. If the cost of keeping 5 goats is the same as the cost of keeping 1 cow, what will be the cost for keeping 50 cows and 30 goats for 12 days?
A. Rs.1104
B. Rs.1000
C. Rs.934
D. Rs.1210

ANSWERS AND SOLUTION :
1(B)Explanation:
C's 1 day's work = 1/3 - (1/6 + 1/8) = 1/3 - 7/24 = 1/24
A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
C's share (for 3 days) = Rs. (3 x 1/24 x 3200) = Rs. 400.

2(C)Explanation :
Work done by P in 1 hour = 1/8
Work done by Q in 1 hour = 1/10
Work done by R in 1 hour = 1/12
Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120
Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60
From 9 am to 11 am, all the machines were operating.
Ie, they all operated for 2 hours and work completed = 2 × (37/120) = 37/60
Pending work = 1- 37/60 = 23/60
Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11
which is approximately equal to 2
Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm.

3(B)Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes (3/2 x 60) = 90 days.
So, A takes 30 days to do the work.
A's 1 day's work = 1/30
B's 1 day's work = 1/90
(A + B)'s 1 day's work = (1/30 1/90) = 4/90 = 2/45
So  A and B together can do the work in 45/2 = 22 1/2 days.

4(C)Explanation :
Work done by P in 1 day = 1/23
Let work done by Q in 1 day = q
q × (130/100) = 1/23
=> q = 100/(23×130) = 10/(23×13)
Work done by P and Q in 1 day = 1/23 + 10/(23×13) = 23/(23×13)= 1/13
=> P and Q together can do the work in 13 days

5(A)Explanation:
Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = 1/10  and 26x + 48y = 1/2,.
Solving these two equations, we get : x = 1/100 and y = 1/200 .
(15 men + 20 boy)'s 1 day's work = (15/100 + 20/200) = 1/4
So,  15 men and 20 boys can do the work in 4 days.

6(C) Explanation
By basic formula:
M1 = 40, D1 = 8, W1 = 60(cutting of trees is taken as work)
M2 = 40 - 8 = 32, D = 12, W2 = ?
Putting the values in the formula
M1 D1 W2 = M2 D2 W1
We have , 40 x 8 x W2 = 32 x 12 x  60
or, W2 = (32 x 12 x 60)/(40 x 8) = 72

7(C)Explanation:
A's 1 hour's work = 1 /4 ;
(B + C)'s 1 hour's work = 1/3 ;
(A + C)'s 1 hour's work = 1/2 .
(A + B + C)'s 1 hour's work = (1/4  + 1/3) = 7/12
B's 1 hour's work = (7/12 - 1/2) = 1/12 .
So, B alone will take 12 hours to do the work.

8(B)Explanation :
Work done by P in 1 day = 1/20
Work done by Q in 1 day = 1/12
Work done by P in 4 days = 4 × (1/20) = 1/5
Remaining work = 1 – 1/5 = 4/5
Work done by P and Q in 1 day = 1/20 + 1/12 = 8/60 = 2/15
Number of days P and Q take to complete the remaining work = (4/5) / (2/15) = 6
Total days = 4 + 6 = 10

9(C)Explanation :
Wages of 1 woman for 1 day = (21600)/(40 x 30)
Wages of 1 man for 1 day = (21600×2)/(40×30)
Wages of 1 man for 25 days = (21600×2×25)/(40×30) = 1080000/1200=900
Number of men = 14400/900 =16

10(A)Explanation :
Assume that cost of keeping a cow for 1 day = c ,
cost of keeping a goat for 1 day = g
Cost of keeping 20 cows and 40 goats for 10 days = 460
Cost of keeping 20 cows and 40 goats for 1 day = 460/10 = 46
=> 20c + 40g = 46
=> 10c + 20g = 23 ---(1)
Given that 5g = c
Hence equation (1) can be written as 10c + 4c = 23 => 14c =23
=> c=23/14
cost of keeping 50 cows and 30 goats for 1 day
= 50c + 30g
= 50c + 6c (substituted 5g = c)
= 56 c = 56×23/14
= 92
Cost of keeping 50 cows and 30 goats for 12 days = 12×92 = 1104

Monday, 14 August 2017

Time and Work


Time and Work

1. 12 Men work 9h/ day to complete 40% of the work in 30 day. The rest work is done by 15 men,6h / day. Then workdone in how many days.
(a) 45
(b) 54
(c) 47
(d) None of these


2. 120 workers can complete a piece of work in 85 days and each worker works 10h/day. All worker start the work, after 10 day all goes to strike. Due to strike, 25 day work stop. How many more worker employed to finish the remaining work if each worker works 8h / day.
(a) 105 
(b) 75
(c) 101
(d) 100

3. In a hotel , food material available for 200 student for 50 days. After 10 days , 50 more students join the hostel. The rest food material a available for how many days.
(a) 22 days
(b) 25
(c) 32 days
(d) None of these

4. 12 male complete a piece of work in 4 days. 15 female complete the same work in 4 days. 6 male start the work. After 2 days all male left the work. How many female required to finish the remaining work complete in 3 days. 
(a) 20 
(b) 15
(c) 10
(d) None of these

5. Work of 4 male is equal to work of 6 female and 9 female is equal to 12 Boys. 8 male and 6 female together work 8 hr/day to complete a work in 15 days. 2 male and 3 female and 4 Boy together work 6hr/day to complete that work so how many day will taken by them.
(a) 30 days
(b) 40 days
(c) 34 days
(d) None of these

6. A , B can do a work in 20 and 30 days. Starting with A work doing by alternate day then in how many days work completed.
(a) 20
(b) 10
(c) 24
(d) 14

7. A , B, C along complete a work in 15 , 20 and 30 days. All together start the work, After 4 days, A left the work, Next after 4 days B left the work. Rest work done by c. they got Rs. 4500 for whole work. Find the share of B
(a) Rs. 1000
(b) Rs.1800
(c) Rs. 2000
(d) RS.3000

8. A, B, C fill a tank in 15, 20 & 30 hr. All pipe opened together. After sum hours closed the pipe A. After 1 hour close the pipe B. The rest work done by C in 5 hour. Then how many times pipe A was closed
(a) 10
(b) 5
(c) 3
(d) 4

9. Two inlet pipe A & B can fill the tank in 20 & 30 hr. Starting by A both pipe open alternately. So tank will be fill after how many time?
(a) 24 hr
(b) 20 hr
(c) 30 hr
(d) None of these

10. Two inlet pipe A & B can fill a tank in 25 min & 20 min. But due to same disturbance in pipe, 5/6th from pipe A, & 2/3rd form pipe B water flow. Both pipe fill the tank in how many min?
(a) 15 min
(b) 20 min
(c) 10 min
(d) None of these

ANSWERS WITH SOLUTIONS

1. (b) Men 1*day1*hour1/work1 = Men2*day2*hour2/work2
       12*30*9/40% = 15*days*6//60%
         days =  54

2.  (a) Men1*day1*hour1/work1 = Men2*day2*hour2/work2
         120*85*10 = (120*10*10 + 50*x*8)
        x = 225 men
      so more worker required 225-120 = 105

3.  (c) Initial student*remaining days = after joining total student* x
        200*40 = 250*  x
         x = 32  days
4.   (b)12m ------> 4 15 F -----> 4
      So 12m * 4 = 15F * 4
     4 m = 5F
     1m = 5/4 f
    Let take F = x
   So 6m * 2 + xF * 3 = 15F * 4
    x = 15
5. (b)4m = 6F
   2m = 3F
   Similarly
   9F = 12B
   3F = 4B
   Work completed by
   ( 8 M x 6F) x 8 x 15 = ( 2M + 3F + 4B) x 6 xD
    D= 40 days
6.(c)

7.(b)   A ‘s 4 days work = 4 x 4 = 16
     B’s 8 days work = 3 x 8 = 24
    Remaining work = 60 – 24 – 16 = 20
  20’ wo rk complete by C in = 10
  So A: B: C = 16: 24: 20
  So share of B = Rs. 1800
8.(b)A = 15
   B = 20
  C = 30
   Unit by A, B and C is 4, 3, 2
   C’s work = 2 x 5 = 10
   B’s = 5
   Remaining work = 60 – 15 = 45
  This work done by A + B + C = 45/9 = 5 hrs.
  A was closed after 5 hrs.

9.(a) Pipe A contribution = 1/20
   pipe B contribution = 1/30
    A + B =  1//20 +   1/30 = 5/60
  1/12=  12 days *2= 24 days

10. (a)  water flows from pipe A = 25*6/5
         water fows from pipe B = 20*3/2
          A + B = 1/30 +1/30 = 2/30
          so taank filled by A+B = 15  mins.